The Civic Whare, Exhibition and Museum site is ramping up the works as the main build starts above ground. Prior to Christmas the ground improvement works were completed and over the last month the rainwater tanks have been installed below ground.
A crane is being erected in the center of the site to do the heavy lifting on CWEM. If the weather behaves, the crane is expected to be put up 5/6/7 June. There will also be some adjustment made to the ComHub crane at the same time. The site team is not expecting significant disruption to the surrounding streets but there may be some Stop/ Go signs operating at the site entry points. We apologise for any inconvenience experienced during this time.

Above: CWEM site 23/05/25