CWEM May 2025 Update

The Civic Whare, Exhibition and Museum site is ramping up the works as the main build starts above ground. Prior to Christmas the ground improvement works were completed and over the last month the rainwater tanks have been installed below ground. A crane is being erected in the center of the site to do the … Continue reading CWEM May 2025 Update

RAP pile update 22 November

RAPS piling continues well this week with the team hitting the 50% mark! The contractors moved the piling equipment to the western end of the site this week and next week will start at the Hamilton Street side before moving operations south towards Baycourt.

Ground improvements update 1 November

Piling work progressed well this week for a short week with 96 further aggregate piles installed. Next week the team aims to complete the eastern part of the site before moving the equipment to the top of the site nearer to Durham Street.

RAP update 25 Oct 2024

Progress on site slowed this week due to some restricted work hours that were put in place to give some respite for neighbours. The team are just over one third of the way through the ground improvements for CWEM.

CWEM Piling Update 18 October

Four weeks into the RAPs piling programme and our contractors are continuing to make excellent progress. By the end of the day the area under the future exhibition building will be completed! The team will be working on more of the perimeter piles next week as they continue east toward Willow Street.