Sheet Piling Update 9 August

The sheet piling has finished ahead of schedule! Thank you for your patience while the contractors have been doing this work. LT McGuinness and their team are still making progress on site installing anchors and doing the bulk excavation in preparation for the next stage of noisy work (RAP piling) which is programmed to begin on September 9th. We will be in touch with more information about the RAP piling closer to starting.