The CWEM sheet piling has been going well and at the end of the first week contractors are 15% of the way through. Next week they will continue down to the corner of Hamilton and Willow Streets. Once that is done, the pilers will go back to the spot opposite the Watts and Hughes carpark and work up the hill.
The large concrete breaker that had been working this week has finished and left site.