Since our last update, the Contractor has been making good progress on the installation of RAPs across the Library and Community Hub site with approximately 75% of the RAP installation complete.
The remaining RAPs are expected to be completed in the coming weeks which will allow the Load Transfer Platform, a gravel raft used to distribute loads from the building to the RAPs, to commence installation. This is on track to be completed by Mid-April.